Pre-Energization Commissioning (No Load)
-Initial Run (Kick off), Runout check
-Bearing Run Test, Vibration Test, Balancing Test
-Balance, Vibration and Other Mechanical Test
-Over Speed Test
-Mechanical Parts Inspection (before/after over speed test)
-Governor Test / Adjustment for Speed no Load Operation
Post-Energization Commissioning (On Load)
-Unit Simulation (Dry) Synchronization Test
-Unit Real Synchronization Test (1st Synch.)
-Initial Load to 5%-10% of Rated Load (5-10MW)
-Active Load Rejection, Include Vibration & Balancing Test
Initial Load Test by Taking Load in Pre-defineded Step to Full Load (Output Test)
-Synchronization
-Unit Heat Run Test
-Unit Trial Run Test